The objective of the Managing a Stage Boundary process is to:
For exceptions, the objectives of the Managing a Stage Boundary process are to:
Managing a Stage Boundary is not used towards the end of the final stage (unless there is a need to create an Exception Plan) because the activities to review the performance of the final stage are included in the activities to review the performance of the whole project as part of the Closing a Project process.