PRINCE2® 2009 - Closing a Project part 4


Activities

The activities within the Closing a Project process are Project-Manager-oriented and are to:

  • Prepare planned closure
  • Prepare premature closure
  • Hand over products
  • Evaluate the project
  • Recommend project closure

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

Non - PRINCE2 information