PRINCE2 2009 - Tailoring PRINCE2 part 23


Tailoring PRINCE2® to the project environment

Project scale

Simple project

Processes

All processes remain relevant even in simple projects.
However, the Starting up a Project process can usually be handled in a less formal manner.
The Executive and Project Manager should, however, avoid the temptation to bypass it altogether.

In some cases it may be appropriate to combine the Starting up a Project and Initiating a Project processes (i.e. creating the Project Initiation Documentation straight from the mandate and skipping the production of a Project Brief).